I’ve been asked to list and differentiate the various types of contracts that you might use in facilities and project management. I’m going to break these down into three major types of contracts: Fixed Price, cost-reimbursable, and time and materials
With that said, let’s get to it…
These have a clear statement of work, and the buyer accepts a seller’s price for it. In this type of contract, the seller bears the risk. An example of this is a purchase order: It will establish the price, quantity, and date for the deliverable. There are three main types of fixed-price contracts:
The most common. A price is set from the outset and will not change unless there is a change in scope.
This is a contract where buyer and seller share some risk and can both benefit from the seller out-performing agreed-upon metrics. In this type of contract, a ceiling price is established (the maximum amount the buyer will pay). Then both parties agree upon a target cost (FP) and the target fee (IF). Both added together become the target price. Finally, each agrees to a share ratio of cost overruns or underruns. The share ratio then is used to calculate the point of total assumption (PTA), where the buyer stops contributing to cost overruns and all additional costs incurred come from the seller’s profit. I know that’s confusing, so let’s consider this example.
Let’s assume I want to purchase a custom piece of equipment that a contractor will make. We agree that I will pay no more than $125,000 for this piece of equipment and that it should cost the contractor $100,000 to make. We agree that if he can make the equipment for that, he deserves a $10,000 incentive fee, which means I would pay the price of $110,000. It looks like this:
Target Cost – $100,000
Target Profit – $10,000
Target Price – $110,000 (target cost + target profit)
Ceiling Price – $125,000
Next, assume we agree to an 80/20 share ratio. That means that if the contractor is able to make the equipment for less than $100,000, his profit goes up by $.20 for every dollar he saves. Alternatively, any costs beyond $110,000 will be paid 80% by me and 20% by the contractor, which eats into his profit. It looks like this:
Share Ratio – 80% buyer, 20% seller
At some point, because I’m not paying any more than $125,000 total, the share ratio goes to 100% contractor and 0% me. This is the PTA and is calculated like this:
PTA – ((ceiling price – target price)/buyer’s share ratio) + target cost
PTA = (($125,000- $110,000) / 0.8) + $100,000
PTA = $18,750 + $100,000
PTA = $118,750
Therefore, once costs go above $118,750, the contractor incurs 100% of them. The contractor can still make a profit (up until the cost reaches $125,000), but each additional cost eats into it.
This is a third type of fixed-price contract and is used for contracts that span multiple years.
These contacts first reimburse the seller for all actual costs incurred and then add a fee for the seller’s profit. In this type of contract, the majority of the risk falls on the buyer and is less desirable because of it. These types of contracts are more appropriate if there is not a clear statement of work in the beginning of the project during the negotiation process or when there are risks present too high for the seller to accept in a fixed price. There are several types of cost-reimbursable contracts:
T&M (time and materials) contracts are a hybrid of both fixed price and cost-reimbursable and are used when a clear statement of work cannot be generated. An example of this is using set professional hourly rates (for instance attorney fees) when the scope (number of hours the buyer will need) is unclear. It is always a good idea to establish a ceiling or a not-to-exceed (NTE) price in this type of contract to avoid massive cost overruns.
Other types of contracts do exist, and it will benefit you to become familiar with your particular organization’s contracting procedures and options available to you. For instance, in a previous FM position, we had an IDIQ (indefinite delivery/indefinite quantity) contract with a number of A-Es. This type of contract is a parent contract that comes up for renewal upon expiration at set intervals (i.e., annually or biannually). Underneath the contract, we would issue task orders to engage in A-E services for the design of certain projects. This method allowed the organization to get routine services ordered in a much quicker manner than going through an entire contracting process each time we needed this service. Issuing a task order was much faster because all of the governing terms and conditions were set in the IDIQ. All that had to be specified was the scope of the individual task order.
ABOUT DAN LOWRY
Dan Lowry is a published author and the Director of Facilities at Southern Hills Country Club. In addition to his civilian work, Dan has served in the Oklahoma Army National Guard as a Major for over fifteen years, utilizing his facilities and operations expertise as an engineer. With an MBA in finance, he’s a certified Project Management Professional® through the Project Management Institute® and maintains his credentials as a Facility Management Professional through the IFMA. Dan currently shares his insights on both his LearningFM site as well as his podcast. You can reach out to him by emailing dan@learningfm.com.